Metropolitan Transit Authority of Harris County Brogden Road and Bridge
Houston, Texas
Construction Cost: $1M
Completion Date:
Prepared preliminary engineering and detail design for the reconstruction of a bridge over Hunter's Creek as well as replacement of 1,800 feet of asphalt pavement and utility relocation. The old timber bridge was replaced with a new concrete box beam bridge to accommodate 12-foot traffic lanes, pedestrian walkways as well as adjacent channel lining to prevent erosion.